The Central Florida Expressway Authority (CFX) is designing capacity improvements to State Road 528 / Beachline Expressway from Goldenrod Road to Innovation Way. The seven-mile project will add an additional lane in the eastbound direction of SR 528, expanding the roadway from two to three travel lanes. These capacity improvements projects will greatly increase ease […]
The Central Florida Expressway Authority (CFX) is currently designing a half interchange at SR 429 and Binion Road in Southwest Apopka. This half interchange will improve mobility by connecting a northbound on-ramp and a southbound off-ramp from SR 429 to Binion Road. Currently, in order to access SR 429 in Southwest Apopka, drivers must enter […]
State Road 429 and State Road 414 The project consists of resurfacing SR 429 from Connector Road to Lust Road and SR 414 from SR 429 to west of Marden Road in Orange County. Lane closures and ramp detours will be scheduled during this project but will be done between 8 p.m. and 6 a.m., […]
  • November 3, 2023
  In summer of 2023, the Central Florida Expressway Authority began adding state-of-the-art technology to accommodate Flex Lanes on its system.  The first Flex Lanes will open on State Road 417 and State Road 429, as part of the capacity improvement projects on those roadways.  These lanes will be the first of their kind in […]
The Central Florida Expressway Authority (CFX) is designing the extension of the State Road 414 Expressway. The 2.8-mile project will provide a direct connection between the eastern end of the SR 414 (John Land Apopka Expressway) and Interstate 4 (I-4). The project will provide needed capacity on SR 414, improve system connectivity between SR 429 […]
This project will provide median protection improvements on SR 429 from Seidel Road to Tilden Road and on SR 451 from Ocoee Apopka Road to Marshall Lake Road. The work includes constructing miscellaneous asphalt pavement and guardrail in the median and regrading the shoulder adjacent to existing concrete ditch pavement. Start Date: June 2023 Anticipated […]
The Central Florida Expressway Authority (CFX) has begun to design Phase 1 of State Road 534 (SR 534), formerly known as the Osceola Parkway Extension. This project is part of the Osceola County Expressway Authority’s (OCX) Master Plan adopted by CFX in 2016. SR 534 would form the northeastern section of the beltway around Osceola […]
In February 2021, CFX began the capacity improvements of the southern corridor of SR 417 from four to six lanes (three lanes in each direction) to improve traffic flow on one of CFX’s busiest expressways. The project is also adding wider median shoulders that can temporarily accommodate additional traffic during emergency response events, such as […]
In August 2021, the Central Florida Expressway Authority (CFX), in partnership with Osceola County, began the design of the proposed capacity improvements of County Road 532/Osceola Polk Line Road from Lake Wilson Road to US 17/92. This is being done in conjunction with the planned extension of Poinciana Parkway from its northern end at Ronald […]
The Central Florida Expressway Authority (CFX) is designing the extension of State Road 538/Poinciana Parkway. The extension is being designed in two segments. Segment 1, from Ronald Reagan Parkway to south of US 17/92 and Segment 2, from south of US 17/92 to County Road 532 are expected to improve traffic flow and operations in […]
The Central Florida Expressway Authority (CFX) is building the State Road 516 Lake/Orange Expressway in Lake and Orange counties. Built with innovation in mind, SR 516 will serve as a revolutionary testbed for electric in-vehicle charging. SR 516 will be the most sustainable project ever delivered by CFX. The new 4.4-mile expressway, which is being […]
In January 2022, CFX began the capacity improvements on SR 429 between Tilden Road and SR 414 to improve traffic flow and relieve congestion. These capacity improvements include expanding from four to six lanes (three lanes in each direction). CFX is also adding wider median shoulders that can temporarily accommodate additional traffic during emergency response […]
In partnership with the City of Orlando, CFX is designing improvements to the SR 408/Tampa Avenue interchange near Camping World Stadium. Planned improvements include: A new Tampa Avenue ramp to eastbound SR 408 A new westbound SR 408 ramp to Tampa Avenue A relocated westbound SR 408 ramp to Orange Blossom Trail A relocated Orange […]
To improve traffic flow and relieve congestion at the SR 429/CR 535 interchange, the Central Florida Expressway Authority (CFX) built new ramps to and from Stoneybrook West Parkway. This work, which occurred nearly a mile south of the SR 429/CR 535 interchange, included a new exit ramp from southbound SR 429 to Stoneybrook West Parkway […]
In late January 2020, the Central Florida Expressway Authority worked on the State Road 429/New Independence Parkway Interchange project. Improvements included widening the southbound State Road 429 ramp to New Independence Parkway and adding pedestrian and vehicle signals at both the northbound and southbound directions at the interchange. Work was completed in May 2020. Click […]
The Central Florida Expressway Authority began milling and resurfacing State Road 528 (Martin B. Andersen Beachline Expressway) in east Orange County between State Road 417 (Central Florida GreeneWay) and State Road 520 in summer 2019. Crews completed the 15-mile paving project of the expressway and improved the northbound State Road 417 ramp to westbound State […]
The Central Florida Expressway Authority completed the State Road 417 (Central Florida GreeneWay) / State Road 408 (Spessard L. Holland East-West Expressway) Interchange.  Phase one was the widening of State Road 417 between Berry Dease Road and State Road 408. The 1.6-mile project saw the addition of a travel lane in both directions (from three […]
In October 2017, CFX began widening State Road 408 from east of State Road 417 to east of Alafaya Trail. This 3.24-mile project added a travel lane to State Road 408 in each direction (from two lanes to three lanes), widened the entrance ramp from northbound Alafaya Trail to westbound State Road 408 from one […]
In May 2017, the Central Florida Expressway Authority (CFX) will begin field testing a new, state-of-the-art toll collection system at the State Road 414 (John Land Apopka Expressway) Coral Hills Main Plaza. The new system is designed to replace much of CFX’s existing toll collection system, some of which has been in service for over […]
As part of our mission to ensure the safety of our customers, the Central Florida Expressway Authority (CFX) began work on its Wrong-Way Driving Prevention Program in 2012 in partnership with the University of Central Florida. The program was broken out into three phases. Phase 1 – Completed in May 2013, extensive research was conducted […]
  • October 27, 2016
The Central Florida Expressway Authority continues to improve existing roadways and toll systems, throughout the 125-mile limited-access expressway system in five counties.
To help reduce accident clearance times and improve safety, the Central Florida Expressway Authority (CFX) has partnered with the Florida Department of Transportation, MetroPlan Orlando, the Florida Highway Patrol, and the Orlando Police Department on a collaborative Pilot Project to research advanced technologies and methods for investigating crash scenes. The Crash Scene Investigation Pilot Project […]